5.2 Construction Logistics Plan

Summary

Principal contractors shall develop and/or implement the agreed CLP and ensure it is appropriately reviewed and updated prior to the start of each new phase of construction.

An approved CLP that, as a minimum, shall:

  • have input from significant site and fleet operators
  • have considered, agreed and committed to planned measures where practical
  • have risk-assessed and specified the safest vehicle routes and identified acceptable reasons for deviation
  • define ‘last mile’ vehicle routes to and from site
  • require use of a delivery management system
  • require competent site access traffic marshals
  • remain a live document